Update for all Summer Place owner.
Tower 1
a) Structural work completed 100%
b) Brick work completed 100%
c) Plastering work completed 100% on pool view unit
Tower 2
a) Structural work up to 13 floor slab
b) Brickwork completed up to 8th floor
Tower 3
a) Structural work up to 18th floor slab
b) Brickwork and plastering work completed up to 14th floor
Shop Lot Beside Summer Place "Lots 28"